Souriau USA - Case Study

Problem:

The customer wanted to make a 1970's designed annealing machine more reliable and less labor intensive.

Solution:

PKP transformed the old design of a tube type, micro-switch relay logic machine and updated to today's solid state hardware.

Result:

The customer has taken the labor from 5 hours per 8 hour shift down to just 10 minutes for the entire shift.  The parts have now been to specification 100% of the time.